Current Project: Design & Construct Greenwich Reserve Cricket Nets

Client: Hobsons Park City Council

Overview:

Design and construct new 4 bay synthetic wickets and 1 new turf cricket. These works included new design drawings including structural drawings.

Demolition of existing cricket wicket enclosure.

Excavation works to Cut/Fill, compact new subgrade.

Supply & install new compacted 200mm Type A fill capping layer. Supply and install new stormwater drainage system.

Construct new 4 lane synthetic courts fencing enclosure including new fencing and double gates around turf practice wicket.

Supply, Install & compacted 100mm class 2 crush rock layer with 50mm thick packing dust layer for preparation for the concrete slab.

Construct new 125mmconcreteslabwith new 300mm edge beams, following supply&InstallnewTiger TurfPremiercricket 9mm grass.